Overview​

QC Inspection is where your quality team defines what to check, how many to check, and then records the results for incoming, in-process, final and outgoing goods. It covers four inspection points:

  • Incoming (IQC): inspect received materials and components.
  • In-process (IPQC): inspect product on the line during production.
  • Final (FQC): inspect finished goods before release.
  • Outgoing (OQC): inspect goods before they ship.

The module has two halves:

  1. Setup (usually a QA Manager): the Test Library, Specifications, Sampling Plans, AQL Standards, Inspection Plans and Line Clearance checklist.
  2. Execution (the QA team): Inspections, where you create a lot, capture results and record a disposition.

Open QC Inspection in the sidebar and pick a section from its submenu: Inspections, Retain Samples, Inspection Plans, Specifications, Sampling Plans, AQL Standards, Test Library and Line Clearance. You only see the sections your role has access to.

Key concepts​

How the pieces fit together​

SectionPurpose
Test LibraryReusable master list of tests (pH, Appearance, Net Weight…) with type, severity, method and preferred instrument.
SpecificationsThe acceptance criteria: the tests plus their target and limits for an item, item group or item type.
Sampling PlansHow many units to inspect and how many defects are allowed.
AQL StandardsThe sampling tables that AQL-based plans read their numbers from.
Inspection PlansBinds a scope and inspection point to a specification, sampling plan, disposition workflow and notification groups.
InspectionsThe inspection record itself: the lot, its results and its disposition.

Everything is keyed off scope and inspection point. Scope can be a Specific item, an Item group or an Item type. When a lot is created, the specification and sampling plan are matched narrow to broad: item first, then item group, then item type. Only Effective specifications and Active sampling plans are matched.

Lot statuses​

StatusWhat it means
DraftThe lot has not been started.
OpenThe lot is being inspected, is awaiting disposition, or is on hold.
ClosedA disposition has been recorded. The outcome shows in the Disposition column.
CancelledThe lot was cancelled rather than dispositioned.

The quick filters on the Inspections list break open lots down further: All, Inspection queue, In progress, Awaiting disposition, On hold and Closed.

Specification and sampling plan statuses​

RecordStatuses
SpecificationDraft, Pending approval, Effective, Superseded
Sampling planDraft, Active (older versions are superseded and hidden from the list)

How to set up QC (QA Manager)​

Build the Test Library​

  1. Go to QC Inspection → Test Library and click Add test.
  2. Enter a Name and Code, then choose a Type (Numeric (measured), Pass / Fail or Text / observation) and a Severity (Critical, Major or Minor).
  3. For numeric tests, tick Requires an instrument and optionally pick a Preferred instrument. The preferred instrument drives the calibration check at capture.
  4. Add Method / instructions, and optionally limit the test with Applies to item groups.

Library tests hold what to test. Target and limits belong to each specification.

Create and approve a specification​

  1. Go to QC Inspection → Specifications → New Specification, or open an item in Item Master and use its Specifications tab.
  2. Enter a Name, choose the Scope and select the target item, item group or item type.
  3. Under Characteristics (tests), click + Add from library or Add test. For each test set the Test name, Type (Numeric, Pass / Fail, Text or Attachment), Defect class and, for numeric tests, Target, LSL (min), USL (max) and UOM. Tick Instrument for gauge-based tests.
  4. Click Create. The specification opens as a Draft.
  5. To approve it, use one of these:
    • On the specification page, click Submit for approval, pick the Reviewer and submit. The status becomes Pending approval and the reviewer gets a task. Approval makes the spec Effective. A rejection or send-back returns it to Draft.
    • On the Specifications list, a user who can manage specifications can click Approve on a draft row and confirm with an e-signature.

Approving a new version supersedes the previous effective spec for the same scope. To change an effective spec, open it and click New version.

Create a sampling plan​

  1. Go to QC Inspection → Sampling Plans → New Sampling Plan.
  2. Enter a Plan name, choose the inspection point, the Scope and the target.
  3. Pick a Plan type:
    • AQL standard: choose the AQL standard, the Inspection level and the Switching state (Normal, Tightened or Reduced). Then add one row per defect class under Defect class → AQL %.
    • Custom table: your own fixed plan, with one sample size for the whole inspection plus accept and reject numbers per defect class.
    • √N + 1: raw-material sampling. For N containers received, ⌈√N⌉ + 1 containers are sampled (for example, 25 containers means 6 samples). AQL accept and reject numbers do not apply. Acceptance comes from the specification's lab tests.
  4. For in-process plans, optionally set Samples per collection and Collection interval (min).
  5. Click Create draft. On the Sampling Plans list, click Approve on the draft and confirm with an e-signature. The plan becomes Active.

To change an active plan, click New Version. This creates a draft revision that you edit and approve. Click a plan's name to open a read-only preview with a live sample-size calculator.

How the sample size is picked for AQL plans​

  1. The lot size and the Inspection level give a sample-size code letter. General levels are I, II and III. Special levels S-1 to S-4 give smaller samples. Click the ? next to Inspection level to open Sample-size code letters (Table 1), which shows the grid for the chosen standard.
  2. The code letter, the AQL % and the Switching state then give the sample size and the accept (Ac) / reject (Re) numbers for each defect class.
  3. Under Sample-size preview, enter a Lot size and click Preview to see the code letter, sample size and per-class accept and reject numbers.
tip

A smaller AQL tolerates fewer defects. The dialog shows the typical pairing: Critical ≈ 0.40–0.65 · Major ≈ 1.0–1.5 · Minor ≈ 2.5–4.0. Hover the help icon next to Switching state for guidance on when to move between Normal, Tightened and Reduced.

AQL Standards​

The AQL Standards section lists the Global standards that ship with the system: ANSI/ASQ Z1.4-2008 — Sampling Procedures and Tables for Inspection by Attributes and ISO 2859-1 — Sampling Procedures for Inspection by Attributes — Part 1. It also lists your company's Custom copies.

  • Click View to read a global standard's plan cells. Global standards are read-only.
  • Click Clone, enter a Custom standard name and confirm to make an editable copy. Use Edit cells on the copy to adjust sample size, accept and reject values.
  • Cells marked larger sample or smaller sample are arrow cells. They have no plan of their own and point to the neighboring code letter's plan. The system follows these arrows automatically.

Create an inspection plan​

  1. Go to QC Inspection → Inspection Plans → New Inspection Plan.
  2. Enter a Plan name and choose the inspection point and Scope.
  3. Under What gets applied to lots, choose the Specification and Sampling Plan. Optionally pick groups under Notify groups when PASSED and Notify groups when FAILED. These groups get email only. It does not assign tasks or grant access.
  4. Choose the Disposition workflow (required). This is the approval route a completed lot follows.
  5. Click Create plan.

Configure line clearance​

In QC Inspection → Line Clearance, turn on Require line clearance before start if in-process samples must not be collected until the line has been cleared. The Line Clearance Checklist is a controlled form. Edit it while it is a draft, click Submit for approval, and use Revise checklist to change an approved version.

How to run an inspection​

Create a lot​

  1. Go to QC Inspection → Inspections and click New Inspection.
  2. Choose the Inspection point and Product. Enter the Lot quantity and Quantity UOM, and fill in the reference fields (Supplier, Batch / Lot ref, PO #, Receipt #, Work order, Manufacturing date, Expiry date).
    • Incoming: set the Goods-receipt date, tick COA received under Certificate of Analysis, and use Attach COA to upload the supplier's certificate.
    • In-process: Production line and Work order are required. Optionally set Shift and Operator.
  3. Under Specification & Sampling Plan, review the match. One match is shown read-only. If several match, you pick one. If nothing matches, the dialog tells you to create and approve one first.
  4. For Sampling, keep Sampling plan or switch to Custom table to declare a fixed plan for this lot only.
  5. For a √N + 1 plan, enter Containers received (N). The field shows the computed sample.
  6. Click Create. The sample size is calculated from the sampling configuration.

Import lots from a spreadsheet​

  1. On the Inspections list, click Import CSV.
  2. Click Download template if you need the column layout. inspection_point (INCOMING / IN_PROCESS / FINAL / OUTGOING) and product_sku are required. quantity, batch_number, po_number, receipt_number, work_order and notes are optional.
  3. Choose your file. Each row is previewed as Ready or with its error.
  4. Click Import n lot(s). Each valid row is matched and sized just like a manually created lot.

Check in and capture results​

  1. Open the lot and click Check in. Pick your Shift and, for in-process lots, the Production lot. Checking in makes you the active inspector and starts the inspection. If someone else is checked in, the button reads Take over (check in).
  2. For incoming, final and outgoing lots, choose how to record under Results:
    • Single result: one result per test for the whole lot.
    • Per sample (n=…): a data sheet with one row per sampled unit and one column per test.
  3. Enter values. Each entry is evaluated against the spec limits and shows Pass or Fail. Numeric fields don't accept negative values unless the test's own limits go below zero.
  4. For tests that need an instrument, pick it on the row, or leave the lot default.
  5. Click Save results.

In the per-sample data sheet:

  • Fill ↓ copies the first row's value down a column.
  • Pasting a newline-separated column into a cell fills the rows below it.
  • The comment icon on each row opens comments & evidence for that sample. When a sample has failed, the icon turns red. You can't save until the reason is recorded.
  • Full screen expands the sheet.

:::warning Calibration interlock A test that requires an instrument can only be recorded with an instrument that is in calibration. If the instrument is calibration-tracked and is overdue, or has no recorded calibration, saving that result is blocked. The lot shows a warning with an Open Equipment link. Pick a different instrument on the affected rows, or record a calibration first. Tests that need no instrument, such as visual checks, are not affected. :::

Complete and submit for disposition​

  1. When all results are in, click Complete.
  2. Click Submit for QA Disposition, confirm the reviewer, and click Submit for Disposition. The disposition workflow comes from the lot's inspection plan or your company default.
  3. In-process lots expect a retain sample before submission. If there is none, enter a Reason for no retain sample.

While the lot is awaiting disposition, the reviewer sees an advisory panel:

  • AQL Acceptance: defective units per defect class compared with the plan's accept and reject numbers, with an advisory Accept or Reject. A unit counts once per class, even if several of its tests in that class fail.
  • Lab Acceptance (√N + 1): for √N + 1 lots, any out-of-specification result gives an advisory Reject.

:::note The verdict is advisory The panel shows what the sampling plan says. The disposition is still a decision the reviewer records. :::

How to record the disposition​

  1. The assigned reviewer opens the lot. It shows This lot is pending QA disposition.
  2. Pick a Disposition. The options come from your company's NC Dispositions list.
  3. Enter Disposition notes and click Record Disposition. If the workflow step requires an e-signature, you're asked to confirm with an e-signature.

Most dispositions close the lot. A hold (quarantine) disposition keeps it Open under the On hold filter.

After an adverse disposition​

  • Click Create Nonconformance to raise a draft NC pre-filled from the lot, with the inspection report attached as a PDF. If an NC already exists, View linked nonconformance appears instead.
  • Use Enter disposition notes to add or update the reasoning.
  • Create Event (in the header actions) raises a quality event from the lot.

Reopen for re-inspection​

A QA manager can click Reopen for Re-inspection on a lot that is awaiting disposition, on hold, or closed with an adverse disposition.

  1. Enter a Reason. It is kept in the lot's history.
  2. Choose the Specification, then the Sampling: Existing plan, Custom AQL or Custom table. Custom choices apply to this lot only.
  3. Optionally set Override sample size and change Re-inspection assigned to.
  4. Click Reopen for Re-inspection. Earlier results are kept, and the current disposition is cleared.

In-process inspection (IPQC)​

  • Line clearance: the lot shows a Line clearance banner for the active production lot. Click Record clearance, complete the checklist, and choose Release (pass) or Hold (fail). You can also Save for later. When clearance is required, Collect sample(s) stays locked until the clearance passes.
  • Collect samples: click Collect sample(s), confirm the Production lot (Lot#) and enter the Number collected. Each collection is stamped with the time and you as the inspector.
  • Collection interval: if the sampling plan sets one, the banner shows when the next collection is due. Collect sample(s) unlocks five minutes before that time. The banner turns amber as it comes due and red once it is overdue.
  • Change production lot: click + Add Lot to start a new production lot mid-run. When clearance is configured, you record it right there with Add & release or Add & hold. Use Close lot when a production lot's run is finished.
  • Check out (end shift): releases the lot so another inspector can take over.

Retain samples​

Click Retain Sample in the lot's header actions, or in the Retained Samples card on the right, to register a physical sample kept from the lot. The item, lot number, batch and dates carry across. You choose the sample type (Reserve, Reference or Retention), quantity, storage location and retain-until date. Retained samples are listed under QC Inspection → Retain Samples.

Tips​

  • Scope specifications and sampling plans to an Item group where you can. One setup covers every item in the group.
  • A lot can't be created without a matching effective specification. If no sampling plan matches yet, use a Custom table for that lot.
  • Print report on a lot opens a printable inspection report. On the Inspections list, Print produces an inspection lot register, and the table can be exported to CSV.
  • If inspectors can see setup sections they shouldn't, review their role under Settings → Roles.